Fukushima Daiichi: The Accident

Fukushima Daiichi: The Accident More than one factor alone led to the accident that took place at Fukushima Daiichi on 11 March 2011.

First factor: Earthquake and tsunami
 
As the 9.0 magnitude earthquake hit the Japanese shore, the reactors of the Fukushima Daiichi nuclear power plant shut down automatically to control the nuclear fission. The electrical lines collapsed, but the plant responded as designed, and the earthquake itself did not cause any other problems. The tsunami it triggered, however, did.
 
“The reactors were robust, seismically speaking,” said Gustavo Caruso, Director of the IAEA’s Office of Safety and Security Coordination. “But they were vulnerable to the high tsunami waves.”
 
When the flooding hit, the ‘tsunami walls’ made to protect the plant from such events were too low to prevent the sea water from entering the plant. The water’s strength destroyed some of the structures, and entered the diesel generator room — which was built lower and at a closer distance to sea level than other plants in Japan — affecting Units 1, 2 and 3.
 
“In spite of all the efforts that were made, and in spite of the nuclear power plant structure resisting the earthquake, the tsunami was the main cause that affected the plant’s defence in depth design, bypassing several safety layers and leading to core melts in Units 1, 2 and 3,” Caruso said.
 
Second factor: Design weaknesses
 
“The diesel generators are essential for maintaining the plant’s electrical supplies in emergency situations,” said Pal Vincze, Head of the Nuclear Power Engineering Section at the IAEA. “They were drowned.”
 
If the diesel generator is affected, special batteries can be used to generate electricity, but these have a limited capacity, and, in the case of Fukushima Daiichi, some were also flooded. “In Japan, they put up a heroic fight to get the electrical systems up and running again, but it wasn’t enough,” Vincze added.
 
Without functioning instrumentation and control systems, or electrical power or cooling capabilities, the overheated fuel melted, sank to the bottom of the reactors, and breached the reactor vessels, leading to three meltdowns. In addition, data logs and vital systems operated by safety parameters were also flooded, which meant that there was no way for the operator to monitor what was going on inside the reactors.
 
Third factor: Shortcomings in safety culture
 
As stated in the IAEA report on the Fukushima Daiichi accident, “a major factor that contributed to the accident was the widespread assumption in Japan that its nuclear power plants were so safe that an accident of this magnitude was simply unthinkable. This assumption was accepted by nuclear power plant operators and was not challenged by regulators or by the Government. As a result, Japan was not sufficiently prepared for a severe nuclear accident in March 2011.”
 
This complacency amounted to a ‘basic assumption’ that the plant could cope with anything, whether it was related to technology or nature. When planning, designing and constructing the plant, experts did not properly take into consideration past tsunami experiences.
 
“There was a belief that the plans were safe enough, and that they were fully prepared to face extreme external events,” Caruso said. “It must be noted that the combination of an earthquake of this magnitude and a tsunami is extremely rare, but unfortunately this is what happened.”
 
This basic assumption, combined with a lack of adequate training among operators in accident management and a lack of sufficient compensatory measures against tsunamis, are what led to the accident, Caruso added.
 
Fourth factor: Gaps in the regulatory system
 
The Fukushima Daiichi accident exposed certain weaknesses in Japan’s regulatory framework. According to the Report, responsibilities had been divided among a number of bodies, and it had not always been clear where authority lay. The Report also points out that some of the IAEA safety recommendations made to the regulator had not been implemented, and some international standards had not been met.
 
It must be said, Caruso concluded, that in spite of the core damage that led to the release of radioactive material into the environment, no health effects could be attributable to radiation, because “based on dose data, and environmental and personal monitoring, the effective doses incurred by members of the public were very low and generally comparable with the range of effective doses incurred due to global levels of natural background radiation.”


Все новости за сегодня (27)
09:02, 19 Февраля 26

Новосибирская ТЭЦ-4 заменит детали турбоагрегата №3

дальше..
08:59, 19 Февраля 26

«Мосгаз» прокладывает новый газопровод в Вешняках

дальше..
08:42, 19 Февраля 26

Энергосистема Кировской области получила возможность передачи дополнительной мощности в Центральный энергорайон

дальше..
08:36, 19 Февраля 26

Саратовская ГЭС установила разъединители на открытом распределительном устройстве

дальше..
07:58, 19 Февраля 26

«Мособлэнерго» отремонтировало кабельную ЛЭП в Звёздном городке

дальше..
07:17, 19 Февраля 26

Полярные Зори принимают первый этап спартакиады «Росэнергоатома»

дальше..
05:34, 19 Февраля 26

Ленинградская АЭС остановила энергоблок №4 на плановый ремонт с модернизацией

дальше..
05:32, 19 Февраля 26

«Россети Новосибирск» выстраивают конструктивный диалог с малым бизнесом

дальше..
05:20, 19 Февраля 26

Филиал «НИУ МЭИ» в Смоленске подготовит специалистов для Смоленской АЭС-2

дальше..
05:00, 19 Февраля 26

Кызылская ТЭЦ в 2026 году построит в столице Тывы 5,5 км теплосетей

дальше..
04:57, 19 Февраля 26

Контроль за строительством очистных сооружений будет обеспечен через онлайн-камеры

дальше..
04:53, 19 Февраля 26

Березовская ГРЭС вывела в капремонт энергоблок №3

дальше..
04:48, 19 Февраля 26

Международная зимняя школа «Обнинск Тех» собрала студентов из 47 стран

дальше..
04:46, 19 Февраля 26

В День книгодарения Богучанская ГЭС пополнила фонды школ и библиотек

дальше..
04:44, 19 Февраля 26

«Владимирэнерго» работает в режиме повышенной готовности

дальше..
04:12, 19 Февраля 26

«Росатом» трудоустроит более 1500 студентов на стройплощадки атомной отрасли в России и за рубежом

дальше..
04:09, 19 Февраля 26

В Вологодской области проложен распределительный газопровод в поселке Дубовское

дальше..
04:06, 19 Февраля 26

«ОДК-Сатурн» внедрил роботизированный комплекс для обработки лопаток двигателей

дальше..
03:58, 19 Февраля 26

Госдума РФ ратифицировала протокол с Китаем по проекту «Ямал СПГ»

дальше..
03:49, 19 Февраля 26

Строительная готовность завода по производству полиэтилена в Казахстане достигла 22%

дальше..
03:42, 19 Февраля 26

На Каме существенно превышены среднегодовые показатели снегозапасов

дальше..
03:29, 19 Февраля 26

В 2025 году по программе МиРЭК в Приморье введено 88 МВА трансформаторных мощностей

дальше..
03:26, 19 Февраля 26

«РН-Юганскнефтегаз» обеспечил экипировкой воспитанников спортивной школы Горноправдинска

дальше..
03:23, 19 Февраля 26

В Великих Луках введен в эксплуатацию газопровод в районе «Рабочий поселок»

дальше..
03:17, 19 Февраля 26

Запорожская АЭС получила лицензию Ростехнадзора на эксплуатацию энергоблока № 2 Запорожской АЭС

дальше..
03:15, 19 Февраля 26

Энергетики ТЭЦ «Восточная» отправили в зону СВО добровольческую помощь

дальше..
03:10, 19 Февраля 26

«Газпром трансгаз Екатеринбург» превысил плановые показатели экономии энергоресурсов за 2025 год

дальше..
 

Поздравляем!
Партнёрству «Кузбассразрезугля» и БЕЛАЗа — 60 лет Партнёрству «Кузбассразрезугля» и БЕЛАЗа — 60 лет

История сотрудничества началась, когда первый белорусский самосвал вышел в кузбасский угольный забой. А дальше — шестьдесят лет новых моделей, производственных рекордов и инженерных решений. Шли годы, самосвалы становились мощнее, а объёмы добычи — больше.



О проекте Размещение рекламы на портале Баннеры и логотипы "Energyland.info"
Яндекс цитирования         Яндекс.Метрика