INTER RAO UES Group launched a new 450 MW CCGT unit at Urengoyskaya TPP09.11.12 19:20
The new 450 MW CCGT steam-gas unit increased the installed capacity of Urengoyskaya TPP from 24 MW to 474 MW.
The unit meets the latest environmental safety and power efficiency standards. It uses a combination of gas and steam turbine units in a combined cycle to produce additional heat and electricity thus increasing the overall energy efficiency. With 52.5% energy efficiency, the new power generation unit significantly outperforms traditional gas turbine units (35-40%) while reducing fuel consumption up to 20-25% compared to steam power plants.