Turboatom completed the manufacture of the second hydro unit for Kamskaya HPP03.06.13 08:17
OJSC "Turboatom" (Ukraine) has completed production of the second hydro unit from four for Kamskaya HPP (Russia). In May 2013 OJSC "Turboatom" carried out functional and oil tests of runner turbine.
In the presence of the customer’s representatives specialists of "Turboatom" verifies the workability of runner on the identity of the turn blades, possible oil leakage and the level of commuting efforts. Under results of work was signed the record of acceptance, that all controlled parameters corresponds to the norms. Till the end of May the equipment will be shipped to the plant. Previously, the plant had produced and shipped guide vanes, turbine cover with a control ring and the mechanisms of the turbine. Экологичный коттедж появился в подмосковном Новом Ступино Строительство модульных зданий Каркасный дом под ключ Основные этапы офисного переезда
|
|
|