Eng - News
Boguchanskaya hydropower plant launches fifth 333 MW unit14.11.13 10:43
JSC RusHydro announces that the fifth hydropower unit was commissioned and put into commercial operation at the Boguchanskaya hydropower plant (a 50/50 JV of RusHydro and UC RUSAL), adding 227 MW (current available capacity due to lower head) to the plant’s working capacity.
The first three 333 MW hydropower units of the Boguchanskaya HPP were put into operation on November 26, 2012, the fourth hydropower unit was launched on January 21, 2013. The plant has started commercial supplies to the wholesale electricity and capacity market from December 1, 2012. Average daily output in October amounted to 16.36 GWh. Since its launch the Boguchanskaya HPP has supplied 4,169 GWh to the wholesale electricity and capacity market, including 3,752 GWh in 2013. Самолет на солнечных батареях пересечет Америку Электрический штабелер – верный помощник на складе Проектирование искусственного освещения
|
|
|