Repair Program of IDGC North-West in 2011 will exceed 1.5 billion rubles05.03.11 10:00
Costs of IDGC North-West for performing of the repair program in 2011 are planned in the amount of 1,565.9 million rubles. This is 27% more than repair program of the previous year.
In 2011, IDGC North-West plans to increase the repair program. Major repairs of power lines will be increased by 22% in comparison with the plan of 2010, clearance of overhead lines will be increased by 16%, by 38% will increase the costs for repairing of substations, by 80% - the cost for repair of production buildings.