LLC «EDC-NG» is completing working on the Razdan HPP power unit 5 modernization20.05.10 13:36
LLC «Engineering & Design center of New Generation» is completing working on the Razdan HPP power unit 5 modernization project (Republic of Armenia).
The LLC «EDC-NG» specialists have corrected major drawings and submitted the power unit main building new design documentation to the customer. Water heating boilers’ design is finished, they are put in operation as of today. The customer has received major and auxiliary equipment installation drawings, architectural, construction and process solutions for the main building and accessory premises. Principal electric diagram is prepared. Total volume of the works done on construction and mechanical project parts is more than 90%.