Construction of ‘November 7th New’ mine officially launched13.11.18 08:07
After obtaining the licence, SUEK Kuzbass prepared a plan for uncovering and developing the Sychevsky-I seam, together with design documents for rail and belt inclines, and the organisation also constructed a temporary fan installation and the collar and underground components of the rail and belt inclines.
The planned launch date for the first longwall is 2020. The Sychevsky-1 seam thickness is 4.5 m, the stope length is 360 m, and the design capacity is 3.5 million tonnes per year. In order to launch the first longwall, it is necessary to drill 13.7 km, including 4.7 km of capital and 9.0 km of preparatory development. The mine will be equipped with modular central drainage treatment facilities. Similar facilities are now used to treat water at the Rubana mine in Leninsk-Kuznetsky and at the Yalevskogo and Taldinskaya-Zapadnaya 1 mines in the Prokopyevsky district. The innovative equipment supplied by the German company EnviroChemie GmbH makes it possible to reuse more than half of the treated water for process needs of the companies. The rest of water discharged into natural water bodies meets all sanitary standards.
Читайте также:
|
|
|
О проекте
Размещение рекламы на портале
Баннеры и логотипы "Energyland.info" |
|