Zaporozhtransformator has successfully tested reactors for Georgia23.10.15 09:11
“Zaporozhtransformator” PJSC (ZTR) has successfully tested 3 reactors rated for 60 MVAr, 500 kV for new substation Jvari (Georgia).
Based on terms of the Contract, ZTR should in all manufacture and supply for the substation 7 units of equipment with total capacity 848 MVA: 4 autotransformers 167 MVA, 500kV, and 3 reactors.
Testing of the first reactor were carried out with witness of General Contractor – the largest power company of Portugal “EFACEC”. As a result the test report was signed without remarks.