Berezovskaya GRES 3rd Power Unit Connected to the United Energy System of Siberia21.08.15 10:19
E.ON Russia Berezovskaya GRES Unit №3 was hooked up to the power grid. Synchronization of the 3rd power unit with the UES of Siberia allowed starting the final stage of tests at the new unit.
Within a few days, in line with a special program, the main unit controllers will be adjusted, frequency and capacity overall primary control response will be tested, turbo generator load-bearing characteristics will be measured.
Thereupon, the unit complex test and certification tests are to be carried out.