Alstom commissions new equipment at two new units of Novogorkovskaya power plant04.01.15 06:07
Two new combined-cycle units based on GT13E2 gas turbines by Alstom were commissioned at Novogorkovskaya Thermal power plant in Russia. With a total capacity of 350 MW, the new units will help nearly double the electrical capacity of Novogorkovskaya power plant, which was commissioned in 1956.
The construction of the new units was launched in December 2012. This project is part of the frame agreement signed in 2011, between Alstom and Renova Group regarding the supply of five of Alstom's GT13E2 gas turbines of 180 MW each for IES-Holding: for Novogorkovskaya (2 turbines) and Nizhneturinskaya (2 turbines) thermal power plants (TPP) and 1 turbine for Akademicheskaya power plant.