Eng - News
RAO UES of the East arranges GTU foundations at Vostochnaia CHPP19.08.14 13:49
RAO Unified Energy Systems of the East (member of RusHydro Group) proceeded to arrangement of the pile field to be used for foundations of gas turbine units at Vostochnaia CHP plant located in the capital of Primorye and currently being under construction.
As of today, contractors have completed arrangement of a piled foundation for GTU No. 3. Reinforcement of the footing and arrangement of piled foundations for GTU No. 1 and GTU No. 2 are currently in progress. Concrete casting of the foundations for all three GTUs is scheduled to be fully completed by the beginning of October.
Читайте также:
|
|
|
О проекте
Размещение рекламы на портале
Баннеры и логотипы "Energyland.info" |
|