Stroytransgaz will build a new power transmission line in Rostov Region11.03.13 08:26
PJSC Stroytransgaz has won the tender to sign a contract with Federal Grid Company of Unified Energy System to build the 500kV HV overhead line, ‘Rostov NPP – Tikhoretskaya №2’, with extension of the 500 kV Tikhoretskaya substation.
As part of the project, Stroytransgaz will also renovate the 500 kV Shakhty substation and line cells at the 500 kV Budyonnovsk and 500 kV Yuzhnaya substations, and will build two deicing units (by short-circuit currents), ZKRP-1 and ZKRP-2, and one deicing switching unit, PPPG-2. The company will also renovate relay protection devices (busbar protection) at the Shakhty, Yuzhnaya and Budyonnovsk subtations.